Concrete Repair Program

The Concrete Repair Program (Sidewalk Replacement and Utility Dig Up Program) is a customer-based program designed to repair concrete throughout the Village. Repairs are usually warranted when the concrete is not draining correctly, deteriorating, or heaving from tree roots. The program does not include driveways or driveway aprons as they are the homeowners responsibly to maintain. The program also includes the repair of areas damaged by a utility dig ups such as a water main break. 

Construction Updates

Construction schedules change frequently due to weather, supply issues, etc. Check this page for the most up-to-date information on Concrete Repair Program projects.

Week of September 18

Concrete removal and replacement expected to start on September 19th or 20th for List #2. Contractor will pass out 24 hour notification if driveway access is impacted by removals.

Addresses included in List #2:

  • 581 E Granville
  • 565 Rodenburg Rd
  • 636 Pinecroft Dr
  • 652 Hazel Ct
  • 455 E Foster Ave
  • 621 & 617 White Oak
  • 608 and 612 White Oak Dr
  • 331 Schreiber Ave
  • 438 Dee Ln 
  • 748, 752, 756 Rodenburg Road: Prescott Dr to Woodside Ln
  • 831 Yosemite Trail


  • 529 S Park S
  • 215 N Prospect to 101 E Thorndale Ave (N Prospect side of house)
  • 379 Ambleside Dr
  • 101 Mornignside Dr
  • 45 Dover Dr
  • 200 N Garden Ave
  • 625 White Oak Dr
  • 805 Rodenburg
  • 323 Berkshire Terrace to Spring St
  • 332 to 320 Berkshire Terr


Week of June 5

Concrete removals expected to start the week of June 12 on List #1 locations. Contractor will pass out 24 hour notification if driveway access is impacted by removals.

Addresses included in List #1:

  • 841 Cross Creek Dr
  • 630 Cross Creek Dr (side of house)
  • 519 Sequoia Trl
  • 386 Jennifer Ln
  • 323 Eden Ct
  • 281 McWalter Dr
  • 221 McWalter Dr
  • 382 Hillside Dr
  • 437 Springwood Dr
  • 404 Springwood Dr
  • 47 W Devon Ave
  • NEC Devon Ave and Marion St (2 spots)
  • 140 W Devon Ave
  • 235 Arthur Ave
  • 315 Arthur Ave
  • 350 to 365 Arthur Ave
  • 345 Arthur Ave
  • 320 W Devon
  • 237 W Devon Ave
  • 125 W Hattendorf
  • 19 W Hattendorf Ave
  • 506 Dee Ln
  • 670 E Devon Ave
  • 680 Circle Dr
  • 673 Circle Dr (Devon Side)
  • 775 Circle Dr


  • 701 Parkview Ct
  • 206 Plum Grove Rd
  • 331 Catalpa Ave     
  • 231 to 215 E Bryn Mawr Ave
  • 517 Spring St (Berkshire side)
  • 529 S Park St
  • 600 Walnut Oaks Dr
  • 620 Walnut Oaks
  • 440 E Walnut St
  • 514 Winterwood
  • 610 Autumn Dr
  • 745 to 757 Springfield Dr
  • 662 Springfield
  • 450 Avebury Ln
  • 694 Middleton Dr
  • 726 Berwick Pl
  • 405 Dover
  • 170 Chatham
  • 260-254 Rodenburg Rd
  • 815 Mensching Rd
  • 920 Longford Dr
  • 870 Longford
  • 740 Hunter Dr
  • 85 Leawood Dr
  • 514 Congress Circle N
  • 1610 Thornfield Ct


Week of March 27

Project award to Schroeder and Schroeder of Skokie, IL


Week of April 10

Preconstruction meeting held.  Work expected to begin on List 1 locations in mid- to late June.